A school has 3 fax machines. The toner in each machine needs to be changed after about five (5) hours of use.?

A school has 3 fax machines. The toner in each machine needs to be changed after about five (5) hours of use. There is one secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that two (2) fax machines need toner at the same time?

1 Answer

Relevance
  • 7 years ago
    Best Answer

    That is an indeterminant question, as we do not know the amount of fax time used of each machine and it certainly won't be equal. However, based on whats given you could say:

    5 hrs. use / 0.25 service time = 20 / 3 machines = 6.67. Probability of needing to service 2 machines simultaneously is: 1/6.67 = 15%.