不懂這題-專案管理之練習題

這是PMP的問題,不懂為何正確答案原因,希望考過證照的大大能幫忙解釋Daily Question

You are in charge of developing a new product for an organization. Your quality metrics are based on the 80th percentile of each of the last three products developed. This is an example of:

A.Metrics

B.Benchmarking

C.Statistical sampling

D.Operational definitions

正確答案在下面↓

正確答案為 B

1 Answer

Rating
  • 1 decade ago
    Favorite Answer

    答案沒錯, 如果你清楚了解benchmark 的意思, 就能很快選到正確答案

    PMBOK 第三版

    P185

    8.1.2 Quality Planning: Tools and Techniques

    Benchmarking

    Benchmarking involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

    Rita 的 PMP Exam Prep (考PMP 必讀的書哦)

    P243

    Benchmarking Looking at past projects to determine ideas for improvement on the current project and to provide a basis to use in measurement of quality performance.

    題目提到拿已完成的三個產品開發專案來作比較, 很符合benchmark 的意思

    其他的答案就不對了, 這樣說明你可以了解嗎

    Source(s): PMBOK, Rita's book 加上我的經驗(我是PMP)