[管理學]PERT的問題

讀到PERT時,課本提到Events,Activities and critical path

可是看解釋還是不太懂什麼意思

1.Events are end points that represent the completion of major axtivities .

2.Activities represent the time or resources required to progress from one event to another .

3.The critical path is the longest or most time-consuming sequence of events and

activities in a PERT network

Update:

直接翻譯也可

能有自己的解釋更好^^

1 Answer

Rating
  • Favorite Answer

    Events,Activities and critical path 事件、活動及要徑 1.Events are end points that represent the completion of major activities . 1.事件是主要活動完成後的終點。 例如「完成牆壁粉刷」 2.Activities represent the time or resources required to progress from one event to another . 2.活動是指從一次事件到另一個事件之間所需時間或者資源。 例如「牆壁粉刷需要3天 3.The critical path is the longest or most time-consuming sequence of events and activities in a PERT network. 3.要俓是在位於PERT圖中所有的事件及活動裡,耗用時間最長的一條順序路線。  可惜這兒沒辦法畫圖,不然會更清楚

    Source(s): 偶而要畫PERT圖,捷瑞會計師