I am pouring footings for my deck using 12" concrete tubes. Can I add the dry mix and just add water? HELP!!!!
I have bought a deck kit from Menards. This kit included 9 - 12" concrete tubes and 45 bags of 60lb concrete mix. The tubes take 5 bags a piece to fill to the 48" height. I also need to install a concrete anchor at the top of each tube so I can install the 4" x 4" post anchor. I know I do not need footings that deep (48") but I want to use up all the concrete mix so I dont have to return it. Its only $3.00 a bag. More work to return it. My question is - can I pour a bag of dry mix in and just add some water and continue on until all 5 bags are added to the one tube? I most certainly do not want to mix 45 bags by hand.
ill it still except the concrete anchor if I do it that way? Will It also set up so I can attach the post anchor to it? I will leave the tubes in? Please help. I need to get this Deck moving.